PSD MUD  
Email us
+44 (0) 1772 690076
+44 (0) 1772 690840
Search:

 
 

Hong Kong

 
PSD's long lasting relationship with Hong Kong began in 1996 when PSD were approached by Gammon Kvaerner Joint Venture to supply desanding equipment to work in support of a Herrenknecht AVN1800D slurry shield TBM, cutting at 2140mm diameter, for the Central, Western & Wan Chai West Trunk Sewers on Hong Kong Island.  The equipment, an SS240DP desander, was shipped to Hong Kong in 1997.  In 1998, an additional SS240DP desander was shipped and in 1999 an SU8DP desilter was mobilised.  The equipment returned to the UK in December 1999.
 
Further work was secured at Aberdeen (Hong Kong Island) for an SS310DP desander to work in support of a Herrenknecht TBM excavating a cable tunnel through 400MPa rock.
 
Another chapter began in 2001, with PSD being awarded the contract to supply a 900m3/hr slurry treatment plant with supervisor to China Harbour Transfield Joint Venture in support of a Herrenknecht 5.18m diameter TBM excavating a deep sewer for the Kai Tak Transfer Scheme. Equipment was shipped in 2002 and returned to the UK on 2004.  After a very successful project, PSD were asked to supply a 1350m3/hr slurry treatment plant and full time supervisor to work in support of a Herrenknecht 8.0m diameter slurry TBM.  The project consisted of two drives totalling 2.3km for and underground railway tunnel for the Kowloon Canton Railway Corporation.  This project began on site in 2006 and finished in 2008.
 
In 2009, Leighton John Holland JV appointed PSD to supply an STP  to support the tunnelling works for the construction of the Lai Chi Kok Transfer scheme. The 1000m3/hr plant was shipped from the UK in September and commissioned in January 2010. Tunnelling on the first drive was completed in early 2011 and the second drive was completed in December 2011.  Piers Verman, Project Manager for LJHJV commented "Thank you to the PSD team for helping make the LCK project a success. Many people in Hong Kong are impressed with what we have achieved."   Read more
Equipment arriving on site in Kowloon
 
Victoria Harbour from Kowloon at night
 
© 2024  Pigott Shaft Drilling Ltd :  info@psdmud.co.uk : Web Design & Content Management System by fat media